Construction of 132kV Transmission Lines
The particular project comes under the Power System Reliability Strengthening Project (PSRSP) – a top priority project of the Sri Lankan government. 132 kV transmission lines are to be constructed as follows:-
- Matara – Hambanthota (77 km)
- Hambanthota – Thissamaharama (23 km)
- Homagama GSS to Horana – Padukka Line (8 km)
- Baddegama GSS to Ambalangoda – Galle Line (0.5 km)
- Cable Termination Tower at Kelaniya for UG cable termination of Peliyagoda GSS
Tender Eligibility : | As mentioned in the bidding document |
Line Ministry : | Ministry of Power & Energy |
Line Agency : | Ceylon Electricity Board (CEB) |
Project Site : | Sri Lanka |
Bid Security : | LKR 61 million or US$ 0.33 million |
Bid Validity : | 210 days |
Issuance of tender document : | Deadline to collect the bid documents is 08-12-2020 at 15.00 hrs. (local time) |
Tender Document Fee : | LKR. 20,000 (approximately USD 108) |
Pre Bid Meeting : | 04-11-2020 at 10.00 hrs. (local time) |
Estimated Project Cost : | Not Mentioned |
Contract Period : | Not Mentioned |
Tender Closing Date : | 09-12-2020 at 10.00 hrs. (local time) |
Funding : | Loan from Asian Development Bank (ADB) – Loan No. 51122-SRI: Power System Reliability Strengthening Project. |
Tender Code : | VBS/TD/20102020/Y_2 |